Human Resources Project Timeline for Going Live
As of August 10, 2001


Note: This timeline only reflects major activities left to be done and does not list activities that have been completed to date.

Action Person Responsible

Date to be
Completed

Comments
       
Determine pay class and pay cycles to be used and update sample group accordingly HR Project Team 8/15/01 June payroll is finished and Janice Pearsall is evaluating this issue
Determine definition of Start Date for Datatel and update sample group accordingly HR Project Team 8/15/01
Start date will be initial date of hire with OKCCC. Benefits and service date will be adjusted based on adjusted date currently in system.
Bring rest of sample group into test payroll HR Project Team 8/15/01
Adjunct position code issue resolved so this can now be done
Run test payrolls for corrected sample group HR Project Team 8/15/01
Cannot run more June payrolls. Will have to be tested with July payroll
Do new cost records for benefits and batch update for July 1 Carolyn/Linda M. 8/17/01
To be done before 8/22 meeting
Give July 1 increases to sample group HR Project Team 8/17/01
To be done by HR Reps before 8/22 meeting
Run July payroll and Datatel system reports to determine what data is needed for state reporting HR Project Team 8/17/01
To be done on or before 8/22
Fully test July payroll HR Project Team 8/22/01
Define FUND Linda M. 8/22/01
Fix GLs before any live entry Linda M. 8/22/01
Set the Live Flag IT Staff 8/22/01 Must be done before data is entered in live. Enables parallel live processing of payrolls.
Identify reporting needs other than payroll HR Project Team 8/22/01  
Run test payroll on sample group for August in TEST HR Project Team 8/22/01 Be sure to do in test because Parallel Live will be activitated at this time.
Transfer Val Codes to Live Larry 8/30/01 Enter only valid codes —not DO NOT USE
Tranfer Code Files to Live Larry 8/30/01 Enter only valid codes —not DO NOT USE
Put Leave Plans in Live Carolyn 8/30/01 Enter only valid codes—not DO NOT USE and USE 01/01/72 DATE
Set up all positions (BUT DO NOT ASSIGN TO PEOPLE) HR Project Team 9/14/01 Enter only valid position codes (Use 01/01/72 start date)
Tax and Retirement Subroutines Loaded and Tested IT Staff/Datatel Programmer 9/14/01 MUST BE DONE BEFORE ANY POSITIONS ARE ASSIGNED TO EMPLOYEES IN LIVE
Put Benefit plans in Live (Note that any tax sheltered cannot be done until Oklahoma Tax issue is fixed) Carolyn 9/21/01

Enter only valid plans
USE 01/01/72 DATE FOR ALL. (OTRS cannot be done until special programming is complete.)

Attach positions, benefits, leave plans, deductions, taxes, and other deductions to one employee at a time for the sample group and MODL with current pay register HR Project Team 9/21/01

Fix discrepancies as discovered.
CANNOT BE DONE UNTIL SPECIAL PROGRAMMING IS COMPLETE (Use Start Date as defined by OKCCC)

Attach positions, benefits, leave plans, taxes, and other deductions for all current employees AND MODL for at least gross pay HR Project Team 10/15/01 CANNOT BE DONE UNTIL SPECIAL PROGRAMMING IS COMPLETE (Use Start Date as defined by OKCCC)
Enter all new employees and changes in status in both systems HR Reps and Payroll Staff Ongoing to 1/1/02 Systems must match to do parallel payrolls
Complete procedures documentation for Human Resources HR Reps 10/15/01  
Complete procedures documentation for Payroll Payroll Staff 10/15/01  
October 23 and 24 Consulting HR Project Team 10/23 & 24  
Run parallel payroll for October HR Project Team 10/31/01 Identify and correct discrepancies
End User Training     As need identified
Continue to maintain dual systems in legacy and live HR Reps & Payroll Staff Ongoing to 1/1/02 Systems must match to do parallel payrolls
Run parallel payroll for November HR Project Team 11/30/01  
Continue to maintain dual systems in legacy and live HR Reps & Payroll Staff Ongoing to 1/1/02 Systems must match to do parallel payrolls
December 18 & 19 Consulting HR Project Team 12/18 & 19/01  
Run parallel payroll for December HR Project Team 12/21/01  
Prepare system for live payroll IT Staff 1/2/02  
Continue to maintain dual systems in legacy and live HR Reps & Payroll Staff Ongoing to 1/1/02 Systems must match to do parallel payrolls
January 21 and 22 Consulting HR Project Team 1/21 & 22/02  
First live payroll in January HR Project Team 1/18/02  

 

For questions or comments please contact Sherry Hendrix, the Information Technology Project Manager.
shendrix@occc.edu or 682-7827.