| Action |
Person Responsible |
Date to be
Completed
|
Comments |
| |
|
|
|
| Determine pay class and pay cycles
to be used and update sample group accordingly |
HR Project
Team |
8/15/01 |
June payroll is finished
and Janice Pearsall is evaluating this issue |
| Determine definition of Start Date
for Datatel and update sample group accordingly |
HR Project
Team |
8/15/01 |
Start date will be initial date of hire with OKCCC.
Benefits and service date will be adjusted based on adjusted date
currently in system.
|
| Bring rest of sample group into test
payroll |
HR Project
Team |
8/15/01 |
Adjunct position code issue resolved so this can
now be done
|
| Run test payrolls for corrected sample
group |
HR Project
Team |
8/15/01 |
Cannot run more June payrolls. Will have to be tested
with July payroll
|
| Do new cost records for benefits and
batch update for July 1 |
Carolyn/Linda
M. |
8/17/01 |
To be done before 8/22 meeting
|
| Give July 1 increases to sample group |
HR Project
Team |
8/17/01 |
To be done by HR Reps before 8/22 meeting
|
| Run July payroll and Datatel system
reports to determine what data is needed for state reporting |
HR Project
Team |
8/17/01 |
To be done on or before 8/22
|
| Fully test July payroll |
HR Project
Team |
8/22/01 |
|
| Define FUND |
Linda
M. |
8/22/01 |
|
| Fix GLs before any live entry |
Linda
M. |
8/22/01 |
|
| Set the Live Flag |
IT Staff |
8/22/01 |
Must be
done before data is entered in live. Enables parallel live processing
of payrolls. |
| Identify reporting needs other than
payroll |
HR Project
Team |
8/22/01 |
|
| Run test payroll on sample
group for August in TEST |
HR Project
Team |
8/22/01 |
Be sure
to do in test because Parallel Live will be activitated at this time. |
| Transfer
Val Codes to Live |
Larry |
8/30/01 |
Enter
only valid codes not DO NOT USE |
| Tranfer Code Files to
Live |
Larry |
8/30/01 |
Enter only
valid codes not DO NOT USE |
| Put Leave Plans in Live |
Carolyn |
8/30/01 |
Enter only
valid codesnot DO NOT USE and USE
01/01/72 DATE |
| Set up all positions
(BUT DO NOT ASSIGN TO PEOPLE) |
HR Project
Team |
9/14/01 |
Enter only
valid position codes (Use 01/01/72 start date) |
| Tax and Retirement Subroutines
Loaded and Tested |
IT Staff/Datatel
Programmer |
9/14/01 |
MUST
BE DONE BEFORE ANY POSITIONS ARE ASSIGNED TO EMPLOYEES IN LIVE |
| Put Benefit plans in
Live (Note that any tax sheltered cannot be done until Oklahoma Tax
issue is fixed) |
Carolyn |
9/21/01 |
Enter only valid plans
USE 01/01/72 DATE FOR ALL. (OTRS cannot be done until special
programming is complete.)
|
| Attach positions, benefits,
leave plans, deductions, taxes, and other deductions to one employee
at a time for the sample group and MODL with current pay register |
HR Project
Team |
9/21/01 |
Fix discrepancies as discovered.
CANNOT BE DONE UNTIL SPECIAL PROGRAMMING IS COMPLETE (Use
Start Date as defined by OKCCC)
|
| Attach positions, benefits,
leave plans, taxes, and other deductions for all current employees
AND MODL for at least gross pay |
HR Project
Team |
10/15/01 |
CANNOT
BE DONE UNTIL SPECIAL PROGRAMMING IS COMPLETE (Use Start Date as defined
by OKCCC) |
| Enter all new employees
and changes in status in both systems |
HR Reps
and Payroll Staff |
Ongoing
to 1/1/02 |
Systems
must match to do parallel payrolls |
| Complete procedures documentation
for Human Resources |
HR Reps |
10/15/01 |
|
| Complete procedures documentation
for Payroll |
Payroll
Staff |
10/15/01 |
|
| October 23 and 24 Consulting |
HR Project
Team |
10/23
& 24 |
|
| Run parallel payroll
for October |
HR Project
Team |
10/31/01 |
Identify
and correct discrepancies |
| End User Training |
|
|
As need
identified |
| Continue to maintain
dual systems in legacy and live |
HR Reps
& Payroll Staff |
Ongoing
to 1/1/02 |
Systems
must match to do parallel payrolls |
| Run parallel payroll
for November |
HR Project
Team |
11/30/01 |
|
| Continue to maintain
dual systems in legacy and live |
HR Reps
& Payroll Staff |
Ongoing
to 1/1/02 |
Systems
must match to do parallel payrolls |
| December 18 & 19
Consulting |
HR Project
Team |
12/18
& 19/01 |
|
| Run parallel payroll
for December |
HR Project
Team |
12/21/01 |
|
| Prepare system for live
payroll |
IT Staff |
1/2/02 |
|
| Continue to maintain
dual systems in legacy and live |
HR Reps
& Payroll Staff |
Ongoing
to 1/1/02 |
Systems must match to
do parallel payrolls |
| January 21 and 22 Consulting |
HR Project
Team |
1/21 &
22/02 |
|
| First live payroll in
January |
HR Project
Team |
1/18/02 |
|